PSEISPRTE SAP (PS Key Figures: Project Item Scheduling Data) Structure details
Description: PS Key Figures: Project Item Scheduling Data
Structure field list including key, data, relationships and ABAP select examples
PSEISPRTE is a standard SAP Structure so does not store data like a database table does. It can be used to define the fields of other actual tables or to process "PS Key Figures: Project Item Scheduling Data" Information within sap ABAP programs.
This is done by declaring abap internal tables, work areas or database tables based on this Structure. These can then be used to store and process the required data appropriately.
i.e. DATA: wa_PSEISPRTE TYPE PSEISPRTE.
The PSEISPRTE table consists of various fields, each holding specific information or linking keys about PS Key Figures: Project Item Scheduling Data data available in SAP. These include MANDT (Client), POSNR (WBS Element), PSPHI (Current number of the appropriate project), PSTRT (WBS element: Basic start date).. See below for full list along with technical details, documentation, text table, check tables, foreign key relationships, conversion routines, relevant tcodes and example ABAP select code etc. .
Delivery Class:Display/Maintenance via tcode SM30: Display/Maintenance Allowed but with Restrictions
SAP enhancement categories: Not classified
SAP PSEISPRTE structure fields - Full list of fields found in SAP data dictionary
Field | Description | Data Element | Data Type | length (Dec) | Check table | Conversion Routine | Domain Name | MemoryID | SHLP |
MANDT | Client | MANDT | CLNT | 3 | T000 | MANDT | |||
POSNR | WBS Element | PS_POSNR | NUMC | 8 | PRPS | ABPSP | PS_POSNR | ||
PSPHI | Current number of the appropriate project | PS_PSPHI | NUMC | 8 | PROJ | KONPD | PS_PSPNR | ||
PSTRT | WBS element: Basic start date | PS_PSTRT | DATS | 8 | DATUM | ||||
ESTRT | Forecasted start date of the WBS element | PS_ESTRT | DATS | 8 | DATUM | ||||
ISTRT | Actual start date for the WBS element | PS_ISTRT | DATS | 8 | DATUM | ||||
PENDE | WBS element: Basic finish date | PS_PENDE | DATS | 8 | DATUM | ||||
EENDE | Forecasted finish date of the WBS element | PS_EENDE | DATS | 8 | DATUM | ||||
IENDE | Actual finish date of the WBS element | PS_IENDE | DATS | 8 | DATUM | ||||
PDAUR | Length (duration) of the basic dates in the WBS element | PS_PDAUR | QUAN | 5(1) | DAUER_4_1 | ||||
EDAUR | Forecasted length (duration) of the WBS element | PS_EDAUR | QUAN | 5(1) | DAUER_4_1 | ||||
IDAUR | Actual length (duration) of the WBS element | PS_IDAUR | QUAN | 5(1) | DAUER_4_1 | ||||
IEINH | Unit for duration of actual WBS element dates | PS_IEINH | UNIT | 3 | CUNIT | EINHEIT | |||
EEINH | Unit for duration of WBS element planned dates | PS_EEINH | UNIT | 3 | CUNIT | EINHEIT | |||
PEINH | Unit for duration of basic WBS element dates | PS_PEINH | UNIT | 3 | CUNIT | EINHEIT | |||
FLGVG | Indicator: There are activities for the WBS elements | PS_FLGVG | CHAR | 1 | X | ||||
FLGEW | Indicator: Expected dates from the activities | PS_FLGEW | CHAR | 1 | X | ||||
FLGEM | Indicator: Forecast dates set manually | PS_FLGEM | CHAR | 1 | X | ||||
FLGVM | Indicator: Basic dates set manually | PS_FLGVM | CHAR | 1 | X | ||||
FLGIM | Indicator: Actual dates set manually | PS_FLGIM | CHAR | 1 | X | ||||
FLGVI | Indicator: Actual dates from the activities | PS_FLGVI | CHAR | 1 | X | ||||
PSTRM | Earliest scheduled start date (Basic) | PS_GSTRS | DATS | 8 | DATUM | ||||
PETRM | Latest scheduled finish date (basic) | PS_GLTRS | DATS | 8 | DATUM | ||||
ESTRM | Scheduled start date (Forecast) | PS_GSTPP | DATS | 8 | DATUM | ||||
EETRM | Latest scheduled finish date (Forecast) | PS_GLTPP | DATS | 8 | DATUM | ||||
VISTR | Tentative actual start date for WBS element | PS_ISTVORL | DATS | 8 | DATUM | ||||
VIEND | Tentative actual finish date for WBS element | PS_IENVORL | DATS | 8 | DATUM | ||||
PSTRS | Latest scheduled start date (basic) | PS_GSTRE | DATS | 8 | DATUM | ||||
PETRF | Earliest scheduled finish date (basic) | PS_GETRE | DATS | 8 | DATUM | ||||
ESTRS | Latest scheduled start date (forecast) | PS_GSTRP | DATS | 8 | DATUM | ||||
EETRF | Earliest scheduled finish date (forecast) | PS_GLTRP | DATS | 8 | DATUM |
Key field | Non-key field |
How do I retrieve data from SAP structure PSEISPRTE using ABAP code?
As PSEISPRTE is a database structure and not a table it does not store any data in the SAP data dictionary. The ABAP SELECT statement is therefore not appropriate and can not be performed on PSEISPRTE as there is no data to select.How to access SAP table PSEISPRTE
Within an ECC or HANA version of SAP you can also view further information about PSEISPRTE and the data within it using relevant transactions such asSE11 (ABAP Dictionary Maintenance)
SM30 (Maintain Table Data)
SE80 (Object Navigator)
SE16 (Data Browser).