PRPSR SAP (WBS Element Structure for Project Reporting) Structure details
Description: WBS Element Structure for Project Reporting
Structure field list including key, data, relationships and ABAP select examples
PRPSR is a standard SAP Structure so does not store data like a database table does. It can be used to define the fields of other actual tables or to process "WBS Element Structure for Project Reporting" Information within sap ABAP programs.
This is done by declaring abap internal tables, work areas or database tables based on this Structure. These can then be used to store and process the required data appropriately.
i.e. DATA: wa_PRPSR TYPE PRPSR.
The PRPSR table consists of various fields, each holding specific information or linking keys about WBS Element Structure for Project Reporting data available in SAP. These include VSGRUPPE (Group for a project version), VSNUMMER (Number or description of a version), PRCTR (Profit Center), PRNAM (Investment program name).. See below for full list along with technical details, documentation, text table, check tables, foreign key relationships, conversion routines, relevant tcodes and example ABAP select code etc. .
Delivery Class:Display/Maintenance via tcode SM30: Display/Maintenance Allowed but with Restrictions
SAP enhancement categories: Can be enhanced (character-type or numeric)
SAP PRPSR structure fields - Full list of fields found in SAP data dictionary
Field | Description | Data Element | Data Type | length (Dec) | Check table | Conversion Routine | Domain Name | MemoryID | SHLP |
ARNUMMER | Archiving Session Number | ADMI_RUN_D | CHAR | 6 | ADMI_RUN | ||||
VSGRUPPE | Group for a project version | VSGRUPPE | CHAR | 20 | TEXT20 | ||||
VSNUMMER | Number or description of a version | VSNMR | CHAR | 12 | VSNMR | VS2 | |||
PRCTR | Profit Center | PRCTR | CHAR | 10 | CEPC | ALPHA | PRCTR | PRC | PRCTR_EMPTY |
PRNAM | Investment program name | IM_PRNAM | CHAR | 8 | IMTP | IM_PRNAM | IMT | ||
PRPOS | Identification for an investment program position | IM_POSID | CHAR | 24 | POSID | IM_POSID | IMP | ||
PSPID | Project Definition | PS_PSPID | CHAR | 24 | ABPSN | PS_PSPID | PSP | PD_DUMMY | |
POSID | Work Breakdown Structure Element (WBS Element) | PS_POSID | CHAR | 24 | PROJN | PS_POSID | PRO | ||
POST1 | PS: Short description (1st text line) | PS_POST1 | CHAR | 40 | TEXT40 | ||||
POSKI | WBS element short identification | PS_POSKI | CHAR | 16 | PS_PROKI | ||||
ERNAM | Name of Person who Created the Object | ERNAM | CHAR | 12 | USNAM | ||||
VERNR | Number of the responsible person (project manager) | PS_VERNR | NUMC | 8 | TCJ04 | PS_VERNR | |||
VERNA | Name of responsible person (Project manager) | PS_VERNA | CHAR | 25 | PS_VERNA | ||||
ASTNR | Applicant number | PS_ASTNR | NUMC | 8 | TCJ05 | PS_ASTNR | |||
ASTNA | Applicant | PS_ASTNA | CHAR | 25 | PS_ASTNA | ||||
PBUKR | Company code for WBS element | PS_PBUKR | CHAR | 4 | T001 | BUKRS | BUK | ||
PGSBR | Business area for WBS element | PS_PGSBR | CHAR | 4 | TGSB | GSBER | GSB | ||
PKOKR | Controlling area for WBS element | PS_PKOKR | CHAR | 4 | TKA01 | CACCD | CAC | ||
PRART | Project type | PS_PRART | CHAR | 2 | TCJ1 | PS_PRART | |||
STUFE | Level in project hierarchy | PS_STUFE_N | NUMC | 3 | NUM3 | ||||
PLAKZ | Indicator: Planning element | PS_PLAKZ | CHAR | 1 | XFELD | ||||
BELKZ | Indicator: Account assignment element | PS_BELKZ | CHAR | 1 | XFELD | ||||
FAKKZ | Indicator: Billing element | PS_FAKKZ | CHAR | 1 | XFELD | ||||
ZUORD | Network assignment | PS_ZUORD | NUMC | 1 | PS_ZUORD | ||||
KALSM | Costing Sheet | AUFKALSM | CHAR | 6 | T683 | KALSM | |||
ZSCHL | Overhead key | AUFZSCHL | CHAR | 6 | CHAR6 | ||||
ABGSL | Results Analysis Key | ABGR_SCHL | CHAR | 6 | TKKAA | ABGR_SCHL | ACS | ||
AKOKR | Controlling area of requesting cost center | PS_AKOKR | CHAR | 4 | TKA01 | CACCD | CAC | ||
AKSTL | Requesting cost center | PS_AKSTL | CHAR | 10 | CSKS | ALPHA | KOSTL | KOS | |
AKTXT | Description | KLTXT | CHAR | 40 | TEXT40 | ||||
FKOKR | Controlling area of responsible cost center | PS_FKOKR | CHAR | 4 | TKA01 | CACCD | CAC | ||
FKSTL | Responsible cost center | PS_FKSTL | CHAR | 10 | CSKS | ALPHA | KOSTL | KOS | |
FKTXT | Description | KLTXT | CHAR | 40 | TEXT40 | ||||
FABKL | Calendar for the dates in the WBS element | PS_FABKL | CHAR | 2 | TFACD | WFCID | |||
PSPRI | Project priority | PS_PRIOR | CHAR | 1 | CHAR1 | ||||
EQUNR | Equipment Number | EQUNR | CHAR | 18 | EQUI | ALPHA | EQUNR | EQN | EQUI |
TPLNR | Functional Location | TPLNR | CHAR | 30 | IFLOT | TPLNR | TPLNR | IFL | IFLM |
PWPOS | WBS element currency | PS_PWPOS | CUKY | 5 | TCURC | WAERS | |||
WERKS | Plant | WERKS_D | CHAR | 4 | T001W | WERKS | WRK | H_T001W_C | |
TXTSP | Language Key | SPRAS | LANG | 1 | T002 | ISOLA | SPRAS | SPR | H_T002 |
SLWID | Key word ID for user-defined fields | SLWID | CHAR | 7 | TCN00 | SLWID | |||
USR00 | 1st user field for 20 characters - WBS element- | USR00PRPS | CHAR | 20 | USRCHAR20 | ||||
USR01 | 2nd user field 20 digits - WBS element | USR01PRPS | CHAR | 20 | USRCHAR20 | ||||
USR02 | 3rd user-defined field 10 digits -WBS element | USR02PRPS | CHAR | 10 | USRCHAR10 | ||||
USR03 | 4th user-defined field 10 digits -WBS element | USR03PRPS | CHAR | 10 | USRCHAR10 | ||||
USR04 | 1st user-defined field for quantity(length 10,3) WBS element | USR04PRPS | QUAN | 13(3) | USRQUAN13 | ||||
USE04 | 1st user defined field for quantity field unit - WBS element | USE04PRPS | UNIT | 3 | T006 | CUNIT | MEINS | ||
USR05 | 2nd use field for quantity (length 10,3) WBS element | USR05PRPS | QUAN | 13(3) | USRQUAN13 | ||||
USE05 | 2nd user defined field for quantity field unit - WBS element | USE05PRPS | UNIT | 3 | T006 | CUNIT | MEINS | ||
USR06 | 1st user field for values (length 10,3) WBS element | USR06PRPS | CURR | 13(3) | USRCURR13 | ||||
USE06 | 1st user defined field for value field unit - WBS element | USE06PRPS | CUKY | 5 | TCURC | WAERS | |||
USR07 | 2nd user field for values (length 10,3) -WBS element | USR07PRPS | CURR | 13(3) | USRCURR13 | ||||
USE07 | 2nd user defined field for value field unit - WBS element | USE07PRPS | CUKY | 5 | TCURC | WAERS | |||
USR08 | 1st user field for date -WBS element | USR08PRPS | DATS | 8 | USRDATE | ||||
USR09 | 2nd user field for date -WBS element | USR09PRPS | DATS | 8 | USRDATE | ||||
USR10 | 1st user field for 'Ind. for evaluations' WBS elem. | USR10PRPS | CHAR | 1 | FLAG | ||||
USR11 | 2nd user field for 'Indicator for eval.s' WBS elemnt | USR11PRPS | CHAR | 1 | FLAG | ||||
CLASF | Indicator: WBS element used in project summarization | PS_CLASF | CHAR | 1 | XFELD | ||||
SCOPE | Object Class | SCOPE_CV | CHAR | 2 | SCOPE | SCOPE_CV | PCO | ||
XSTAT | Statistical WBS element | PS_XSTAT | CHAR | 1 | XFELD | ||||
TXJCD | Tax Jurisdiction | TXJCD | CHAR | 15 | TTXJ | TXJCD | TXJ | ||
ZSCHM | Interest Profile for Project/Order Interest Calculation | PS_ZSCHM | CHAR | 7 | TPI01 | PS_ZSCHM | |||
IMPRF | Investment measure profile | IM_PROFIL | CHAR | 6 | TAPRF | IM_PROFIL | |||
EVGEW | Aggregation weight for POC (PS progress) | EV_WEIGHTD | DEC | 8 | DEC8 | ||||
AENNR | Change Number | AENNR | CHAR | 12 | AENR | AENNR | AENNR | AEN | |
SUBPR | Sub-project in work breakdown structure | PS_SUBPR | CHAR | 12 | PRTP | PS_SUBPR | |||
PSPCODE | WBS code for project hierarchy | PS_PSPCODE | CHAR | 50 | PS_PSPCODE | ||||
PSTRT | WBS element: Basic start date | PS_PSTRT | DATS | 8 | DATUM | ||||
ESTRT | Forecasted start date of the WBS element | PS_ESTRT | DATS | 8 | DATUM | ||||
ISTRT | Actual start date for the WBS element | PS_ISTRT | DATS | 8 | DATUM | ||||
PENDE | WBS element: Basic finish date | PS_PENDE | DATS | 8 | DATUM | ||||
EENDE | Forecasted finish date of the WBS element | PS_EENDE | DATS | 8 | DATUM | ||||
IENDE | Actual finish date of the WBS element | PS_IENDE | DATS | 8 | DATUM | ||||
PDAUR | Forecast duration | PS_PDAUER_VZ | QUAN | 10(1) | PS_DAUER_VZ | ||||
EDAUR | Duration | PS_EDAUER_2 | QUAN | 10(1) | DAUER_9_1 | ||||
IDAUR | Actual duration | PS_IDAUER_VZ | QUAN | 10(1) | PS_DAUER_VZ | ||||
IEINH | Unit for the length (duration) of the WBS element | PS_EINHT | UNIT | 3 | CUNIT | EINHEIT | |||
EEINH | Unit for the length (duration) of the WBS element | PS_EINHT | UNIT | 3 | CUNIT | EINHEIT | |||
PEINH | Unit for the length (duration) of the WBS element | PS_EINHT | UNIT | 3 | CUNIT | EINHEIT | |||
PSTRM | Earliest scheduled start date (Basic) | PS_GSTRS | DATS | 8 | DATUM | ||||
PETRM | Latest scheduled finish date (basic) | PS_GLTRS | DATS | 8 | DATUM | ||||
ESTRM | Scheduled start date (Forecast) | PS_GSTPP | DATS | 8 | DATUM | ||||
EETRM | Latest scheduled finish date (Forecast) | PS_GLTPP | DATS | 8 | DATUM | ||||
VISTR | Tentative actual start date for WBS element | PS_ISTVORL | DATS | 8 | DATUM | ||||
VIEND | Tentative actual finish date for WBS element | PS_IENVORL | DATS | 8 | DATUM | ||||
VNAME | Joint Venture | JV_NAME | CHAR | 6 | T8JV | ALPHA | JV_NAME | JVV | |
RECID | Recovery Indicator | JV_RECIND | CHAR | 2 | T8JJ | ALPHA | JV_RECIND | ||
ETYPE | Equity type | JV_ETYPE | CHAR | 3 | T8JE | ALPHA | JV_ETYPE | ||
OTYPE | Joint Venture Object Type | JV_OTYPE | CHAR | 4 | ALPHA | JV_OTYPE | |||
JIBCL | JIB/JIBE Class | JV_JIBCL | CHAR | 3 | T8J6A | JV_JIBCL | JIB | ||
JIBSA | JIB/JIBE Subclass A | JV_JIBSA | CHAR | 5 | T8J6C | JV_JIBSA | JBS | ||
STATXT | Edited status text | STATUSTEXT_2 | CHAR | 80 | CHAR80 | ||||
FRUEHER | Actual start is before earliest scheduled start | FRUEHER_2 | QUAN | 10(1) | DAUER_9_1 | ||||
SPAETER | Actual Finish/Planned Finish After Latest Scheduled Finish | SPAETER_2 | QUAN | 10(1) | DAUER_9_1 | ||||
VERZUG | Duration After Latest Scheduled Finish | VERZUG_2 | QUAN | 10(1) | DAUER_9_1 | ||||
VORBEI | Duration After Earliest Scheduled Start | VORBEI_2 | QUAN | 10(1) | DAUER_9_1 | ||||
VEINH | Unit for Duration of the Delay | VERZ_EINHT | UNIT | 3 | T006 | CUNIT | MEINS | ||
FUNC_AREA | Functional Area | FKBER | CHAR | 16 | Assigned to domain | FKBER | FBE |
Key field | Non-key field |
How do I retrieve data from SAP structure PRPSR using ABAP code?
As PRPSR is a database structure and not a table it does not store any data in the SAP data dictionary. The ABAP SELECT statement is therefore not appropriate and can not be performed on PRPSR as there is no data to select.How to access SAP table PRPSR
Within an ECC or HANA version of SAP you can also view further information about PRPSR and the data within it using relevant transactions such asSE11 (ABAP Dictionary Maintenance)
SM30 (Maintain Table Data)
SE80 (Object Navigator)
SE16 (Data Browser).
Search for further information about these or an SAP related objects