BAPI_BUS2002_ACT_DETAIL SAP (Data Structure: Activity GetData) Structure details

Dictionary Type: Structure
Description: Data Structure: Activity GetData




ABAP Code to SELECT data from BAPI_BUS2002_ACT_DETAIL
Related tables to BAPI_BUS2002_ACT_DETAIL
Access table BAPI_BUS2002_ACT_DETAIL




Structure field list including key, data, relationships and ABAP select examples

BAPI_BUS2002_ACT_DETAIL is a standard SAP Structure so does not store data like a database table does. It can be used to define the fields of other actual tables or to process "Data Structure: Activity GetData" Information within sap ABAP programs.

This is done by declaring abap internal tables, work areas or database tables based on this Structure. These can then be used to store and process the required data appropriately.

i.e. DATA: wa_BAPI_BUS2002_ACT_DETAIL TYPE BAPI_BUS2002_ACT_DETAIL.

The BAPI_BUS2002_ACT_DETAIL table consists of various fields, each holding specific information or linking keys about Data Structure: Activity GetData data available in SAP. These include ACTIVITY (Activity number in network and standard network), DESCRIPTION (Operation short text), PROJECT_DEFINITION (Project Definition), WBS_ELEMENT (Work Breakdown Structure Element (WBS Element)).. See below for full list along with technical details, documentation, text table, check tables, foreign key relationships, conversion routines, relevant tcodes and example ABAP select code etc. .

Delivery Class:
Display/Maintenance via tcode SM30: Display/Maintenance Allowed but with Restrictions
SAP enhancement categories: Can be enhanced (character-type or numeric)


SAP BAPI_BUS2002_ACT_DETAIL structure fields - Full list of fields found in SAP data dictionary

Field Description Data Element Data Type length (Dec) Check table Conversion Routine Domain Name MemoryID SHLP
NETWORKNetwork number NW_AUFNRCHAR12Assigned to domainALPHAAUFNRANR
ACTIVITYActivity number in network and standard network CN_VORNRCHAR4NUMCVVORNR
DESCRIPTIONOperation short text LTXA1CHAR40TEXT40
PROJECT_DEFINITIONProject Definition PS_PSPIDCHAR24ABPSNPS_PSPIDPSPPD_DUMMY
WBS_ELEMENTWork Breakdown Structure Element (WBS Element) PS_POSIDCHAR24PROJNPS_POSIDPRO
CONTROL_KEYControl key STEUSCHAR4Assigned to domainSTEUS
PLANTPlant WERKS_DCHAR4Assigned to domainWERKSWRKH_T001W_C
WORK_CNTRWork center ARBPLCHAR8ARBPLAGR
WORK_ACTIVITYWork involved in the activity ARBEITQUAN7(1) ARBEIT
WORK_UNITUnit for work ARBEITEUNIT3Assigned to domainCUNITMEINS
WORK_UNIT_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
CALCULATION_KEYKey for calculation INDETCHAR1INDET
ACTTYPEActivity Type LSTARCHAR6Assigned to domainLSTARLARLART_EMPTY
PRIORITYPriority NW_PRIOCHAR1Assigned to domainNW_PRIO
MILESTONEUsage MILESTONECHAR5Assigned to domainMILESTONE
DISTRIBUTION_KEYDistr.cap.reqmts (plant maint.,process order, network) CR_VERTNCHAR8Assigned to domainCR_VERTL
NUMBER_OF_CAPACITIESNumber of capacities required ANZKAPINT13INT1
PERCENT_OF_WORKWork percentage APROZENTINT13INT1
EXEC_FACTORExecution Factor AFAKTDEC3AFAKT
BUSINESS_PROCESSBusiness Process CO_PRZNRCHAR12Assigned to domainALPHACO_PRZNRKWP
STD_TEXT_KEYStandard text key KTSCHCHAR7Assigned to domainKTSCH
SUBNETWORK_EXISTSIndicator: Sub-network exists FLG_VABCHAR1X
PROJECT_SUMMARIZATIONInd.: Take Activity Into Account for Project Summarization CLASFCHAR1XFELD
SYSTEM_STATUSIndividual status of an object (short form) J_TXT04CHAR4TEXT4
LANGULanguage Key SPRASLANG1Assigned to domainISOLASPRASSPRH_T002
LANGU_ISO2-Character SAP Language Code LAISOCHAR2LAISO
DURATION_NORMALNormal duration of the activity DAUNORQUAN5(1) DAUER_4_1
DURATION_NORMAL_UNITNormal duration/unit DAUNOREUNIT3Assigned to domainCUNITMEINS
DURATION_NORMAL_UNIT_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
DURATION_MINIMUMMinimum activity duration DAUMINQUAN5(1) DAUER_4_1
DURATION_MINIMUM_UNITUnit for the minimum duration DAUMINEUNIT3Assigned to domainCUNITMEINS
DURATION_MINIMUM_UNIT_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
FLEXIBLE_DURATIONIndicator: flexible duration DAUDEHNCHAR1X
FACTORY_CALENDARFactory Calendar WFCIDCHAR2Assigned to domainWFCIDFCI
REDUCTION_STRATEGYReduction strategy per operation/activity RSTRACHAR2Assigned to domainRSTRA
INFO_RECNumber of Purchasing Info Record INFNRCHAR10Assigned to domainALPHAINFNRINFMEIN_C
VENDOR_NOAccount Number of Vendor or Creditor LIFNRCHAR10Assigned to domainALPHALIFNRLIFKRED_C
PURCH_ORGPurchasing Organization EKORGCHAR4Assigned to domainEKORGEKO
PUR_GROUPPurchasing Group EKGRPCHAR3Assigned to domainEKGRPEKG
MATL_GROUPMaterial Group MATKLCHAR9Assigned to domainMATKLMKLS_WBWG
AGREEMENTNumber of Principal Purchase Agreement KONNRCHAR10Assigned to domainALPHAEBELNKTR
AGMT_ITEMItem Number of Principal Purchase Agreement KTPNRNUMC5Assigned to domainEBELP
PRICEPrice PREISCURR11(2) WERT11
PRICE_UNITPrice Unit PEINHDEC5PACK3
CURRENCYCurrency Key WAERSCUKY5Assigned to domainWAERSFWS
CURRENCY_ISOISO currency code ISOCDCHAR3ISOCD
COST_ELEMCost Element KSTARCHAR10Assigned to domainALPHAKSTARKAT
PUR_INFO_RECORD_DATA_FIXEDIndicator: Purchasing info record data are fixed CN_KZFIXCHAR1XFELD
PLND_DELRYPlanned Delivery Time in Days PLIFZDEC3DEC3
OPERATION_QTYOperation quantity in order unit of measure CX_LOSVGQUAN13(3) MENG13
OPERATION_MEASURE_UNITUnit of Measure for Activity/Operation VORMEUNIT3Assigned to domainCUNITMEINS
OPERATION_MEASURE_UNIT_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
NOT_MRP_APPLICABLEInd: Reserv. not applicable to MRP;Purc. req. not created NODISPCHAR1XFELD
SORTED_BYSort Term for Non-Stock Info Records SORTICHAR10CHAR10
PREQ_NAMEName of Requisitioner/Requester AFNAMCHAR12AFNAM
GR_RCPTGoods Recipient/Ship-To Party WEMPFCHAR12WEMPF
TRACKINGNORequirement Tracking Number BEDNRCHAR10CHAR10
UNLOAD_PTUnloading Point ABLADCHAR25TEXT25
GOODS_RECIEVEDQuantity of Goods Received WEMNGQUAN13(3) MENG13
PURCHASE_REQUISITIONPurchase requisition number CO_BANFNCHAR10ALPHABANFN
PURCHASE_REQUISITION_ITEMItem number of the purchase requisition in the order CO_BNFPONUMC5Assigned to domainBNFPO
PURCHASE_ORDER_EXISTSIndicator: Purchase order exists FLG_PURSCHAR1KREUZ
SERVICE_EXISTSSelection indicator FLG_SELCHAR1XFELD
COMP_CODECompany Code BUKRSCHAR4Assigned to domainBUKRSBUKC_T001
FUNC_AREAFunctional Area FKBERCHAR16Assigned to domainFKBERFBE
BUS_AREABusiness Area GSBERCHAR4Assigned to domainGSBERGSB
PROFIT_CTRProfit Center PRCTRCHAR10Assigned to domainALPHAPRCTRPRCPRCTR_EMPTY
CHANGE_NOChange Number AENNRCHAR12Assigned to domainAENNRAENNRAEN
REFERENCE_POINTReference point for BOM transfer CN_RFPNTCHAR20Assigned to domainCN_RFPNT
CSTG_SHEETCosting Sheet AUFKALSMCHAR6Assigned to domainKALSM
OVERHEAD_KEYOverhead key AUFZSCHLCHAR6CHAR6
TAXJURCODETax Jurisdiction TXJCDCHAR15Assigned to domainTXJCDTXJ
OBJECTCLASS_EXTObject class, language-dependent SCOPE_LDCHAR5CHAR5
ACTIVITY_COSTSCosts in the activity PRKSTCURR11(2) PRKST
OBJECT_CURRENCYObject currency for network activity OWAERSCUKY5Assigned to domainWAERS
OBJECT_CURRENCY_ISOISO currency code ISOCDCHAR3ISOCD
REQ_COST_CENTERRequesting cost center ANFKOCHAR10Assigned to domainALPHAKOSTL
CONSTRAINT_TYPE_STARTConstraint on the basic start date for the activity EINSCHRACHAR1RESTRIKSTR
CONSTRAINT_TYPE_FINISHConstraint on the finish date of the activity EINSCHRECHAR1RESTRIKEND
CONSTRAINT_START_DATEConstraint for activity start (Basic) VORGABESTDDATS8VORGABESTR
CONSTRAINT_START_TIMEConstraint for activity start time (Basic) VORGABESTZTIMS6ATIME
CONSTRAINT_FINISH_DATEConstraint for finish of activity (Basic) VORGABEENDDATS8VORGABEEND
CONSTRAINT_FINISH_TIMEBasic finish time of the activity VORGABEENZTIMS6ATIME
EARLY_START_DATEEarliest scheduled start: Execution (date) FSAVDDATS8DATUM
EARLY_START_TIMEEarliest scheduled start: Execution (time) FSAVZTIMS6ATIME
EARLY_FINISH_DATEEarliest scheduled finish: Execution (date) FSEDDDATS8DATUM
EARLY_FINISH_TIMEEarliest scheduled finish: Execution (time) FSEDZTIMS6ATIME
LATEST_START_DATELatest scheduled start: Execution (date) SSAVDDATS8DATUM
LATEST_START_TIMELatest scheduled start: Execution (time) SSAVZTIMS6ATIME
LATEST_FINISH_DATELatest scheduled finish: Execution (date) SSEDDDATS8DATUM
LATEST_FINISH_TIMELatest scheduled finish: Execution (time) SSEDZTIMS6ATIME
DURATION_SCHEDULEDProcessing time CO_DAUBEAQUAN7(1) DAUER_6_1
DURATION_SCHEDULED_UNITUnit of measure for processing time BEAZEUNIT3CUNITEINHEIT
DURATION_SCHEDULED_UNIT_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
FLOAT_FREEFree float PUFFR_FREIDEC3PUFFER
FLOAT_TOTALTotal float PUFFR_GESMDEC3PUFFER
WORK_ACTUALActual work CO_ISMNWQUAN13(3) MENG13
ACTUAL_START_DATEActual start: Execution (date) ISDDDATS8DATUM
ACTUAL_START_TIMEActual start: Execution/setup (time) ISDZTIMS6ATIME
ACTUAL_FINISH_DATEActual finish: Execution (date) IEDDDATS8DATUMEDR
ACTUAL_FINISH_TIMEActual finish: Execution (time) IEDZTIMS6ATIMEEZR
WORK_FORECASTForecasted work (actual + remaining) OFMNWQUAN7(1) ARBEIT
FORECAST_DURATIONForecasted duration of activity from confirmation PDAUQUAN5(1) DAUER_4_1
FORECAST_DURATION_UNITUnit of the forecasted duration from the confirmation PDAEUNIT3Assigned to domainCUNITMEINS
FORECAST_DURATION_UNIT_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
FORECAST_FINISH_DATEForecast finish date of operation from confirmation CO_PEDDDATS8DATUM
FORECAST_FINISH_TIMEForecast finish time of operation from confirmation CO_PEDZTIMS6ATIME
DISPATCHED_START_DATEDispatched start date for operation EPANFDATS8DATUM
DISPATCHED_START_TIMEDispatched start time for operation EPANZTIMS6ATIME
DISPATCHED_FINISH_DATEDispatched finish date EPENDDATS8DATUM
DISPATCHED_FINISH_TIMEDispatched finish time EPENZTIMS6ATIME
CONSTRAINT_TYPE_FINISH_FCForecast date constraint on activity finish PS_RESTECHAR1RESTRIKEND
CONSTRAINT_TYPE_START_FCForecast date constraint on activity start PS_RESTACHAR1RESTRIKSTR
CONSTRAINT_START_DATE_FCForecasted start date for the activity EWSTARTDDATS8DATUM
CONSTRAINT_START_TIME_FCForecast start time of the activity EWSTARTZTIMS6ATIME
CONSTRAINT_FINISH_DATE_FCForecast finish date EWENDEDDATS8DATUM
CONSTRAINT_FINISH_TIME_FCForecast finish time for the activity EWENDEZTIMS6ATIME
DURATION_NORMAL_FCNormal duration (from forecast) of activity EWDANQUAN5(1) DAUER_4_1
DURATION_NORMAL_FC_UNITUnit for forecast normal duration EWDNEUNIT3Assigned to domainCUNITMEINS
DURATION_NORMAL_FC_UNIT_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
DURATION_MINIMUM_FCMinimum duration (from forecast) for activity EWDAMQUAN5(1) DAUER_4_1
DURATION_MINIMUM_FC_UNITUnit for forecast minimum duration EWDMEUNIT3Assigned to domainCUNITMEINS
DURATION_MINIMUM_FC_UNIT_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
EARLY_START_DATE_FCEarliest scheduled start date (forecast) FPAVDDATS8DATUM
EARLY_START_TIME_FCEarliest scheduled start time (forecast) FPAVZTIMS6ATIME
EARLY_FINISH_DATE_FCEarliest scheduled finish date (forecast) FPEDDDATS8DATUM
EARLY_FINISH_TIME_FCEarliest scheduled finish time (forecast) FPEDZTIMS6ATIME
LATEST_START_DATE_FCLatest scheduled start date (forecast) SPAVDDATS8DATUM
LATEST_START_TIME_FCLatest scheduled start time (forecast) SPAVZTIMS6ATIME
LATEST_FINISH_DATE_FCLatest scheduled finish date (forecast) SPEDDDATS8DATUM
LATEST_FINISH_TIME_FCLatest scheduled finish time (forecast) SPEDZTIMS6ATIME
FLOAT_FREE_FCFree float (from forecast) PPUFF_FREIDEC3PUFFER
FLOAT_TOTAL_FCTotal float (from forecast) PPUFF_GESMDEC3PUFFER
USER_FIELD_KEYKey word ID for user-defined fields SLWIDCHAR7Assigned to domainSLWID
USER_FIELD_CHAR20_1User field with 20 characters USRCHAR20CHAR20USRCHAR20
USER_FIELD_CHAR20_2User field with 20 characters USRCHAR20CHAR20USRCHAR20
USER_FIELD_CHAR10_1User field with 10 characters USRCHAR10CHAR10USRCHAR10
USER_FIELD_CHAR10_2User field with 10 characters USRCHAR10CHAR10USRCHAR10
USER_FIELD_QUAN1User field for quantity (length 10.3) USRQUAN13QUAN13(3) USRQUAN13
USER_FIELD_UNIT1User field: Unit for quantity fields USRUNITUNIT3Assigned to domainCUNITMEINS
USER_FIELD_UNIT1_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
USER_FIELD_QUAN2User field for quantity (length 10.3) USRQUAN13QUAN13(3) USRQUAN13
USER_FIELD_UNIT2User field: Unit for quantity fields USRUNITUNIT3Assigned to domainCUNITMEINS
USER_FIELD_UNIT2_ISOISO code for unit of measurement ISOCD_UNITCHAR3Assigned to domainISOCD_UNIT
USER_FIELD_CURR1User-defined field for values (length 10,3) USRCURR13CURR13(3) USRCURR13
USER_FIELD_CUKY1User field: Unit for value fields USRCUKYCUKY5Assigned to domainWAERS
USER_FIELD_CUKY1_ISOISO currency code ISOCDCHAR3ISOCD
USER_FIELD_CURR2User-defined field for values (length 10,3) USRCURR13CURR13(3) USRCURR13
USER_FIELD_CUKY2User field: Unit for value fields USRCUKYCUKY5Assigned to domainWAERS
USER_FIELD_CUKY2_ISOISO currency code ISOCDCHAR3ISOCD
USER_FIELD_DATE1User field for date USRDATEDATS8USRDATE
USER_FIELD_DATE2User field for date USRDATEDATS8USRDATE
USER_FIELD_FLAG1User-defined field: Indicator for reports USRFLAGCHAR1FLAG
USER_FIELD_FLAG2User-defined field: Indicator for reports USRFLAGCHAR1FLAG
OBJECT_IDObject ID OBJEKTIDNUMC8NUM08PON
CAPACITY_CATEGORYCapacity category QL_KAPARTCHAR3Assigned to domainKAPARTCAA
CONFIRMATION_NUMBERCompletion confirmation number for the operation CO_RUECKNUMC10CO_RUECKRCK
WAGE_TYPEWage Type LOHNARTCHAR4LOART
TIME_TICKETSNumber of Time Tickets LOHNANZDEC3LOHNANZ
CONFIRMATION_SLIPSNumber of confirmation slips CR_RS_ANZNUMC3NUM03
SUITABILITYSuitability QUALFCHAR2Assigned to domainQUALF
POC_AGGREGATION_WEIGHTAggregation weight for POC (PS progress) EV_WEIGHTDDEC8DEC8
STAT_PROFStatus Profile J_STSMACHAR8Assigned to domainJ_STSMA
FORECAST_MATERIAL_COSTSMaterial planning in networks: primary costs MAT_PRKSTCURR11(2) PRKST

Key field Non-key field



How do I retrieve data from SAP structure BAPI_BUS2002_ACT_DETAIL using ABAP code?

As BAPI_BUS2002_ACT_DETAIL is a database structure and not a table it does not store any data in the SAP data dictionary. The ABAP SELECT statement is therefore not appropriate and can not be performed on BAPI_BUS2002_ACT_DETAIL as there is no data to select.

How to access SAP table BAPI_BUS2002_ACT_DETAIL

Within an ECC or HANA version of SAP you can also view further information about BAPI_BUS2002_ACT_DETAIL and the data within it using relevant transactions such as

SE11 (ABAP Dictionary Maintenance)
SM30 (Maintain Table Data)
SE80 (Object Navigator)
SE16 (Data Browser).


Search for further information about these or an SAP related objects



Comments on this SAP object

What made you want to lookup this SAP object? Please tell us what you were looking for and anything you would like to be included on this page!